Estimate how much material to remove from a dig site, the swell factor for hauling, and the cost to excavate. Use the Fill Calculator if you are bringing material in rather than removing it.
Estimate how much material to remove from a dig site, the swell factor for hauling, and the cost to excavate. Use the Fill Calculator if you are bringing material in rather than removing it.
Volume is length × width × depth, with wastage and a compaction factor stacked on top.
cubic_feet = length × width × depth × (1 + wastage%) × (1 + compaction%)cubic_yards = cubic_feet ÷ 27Excavated material expands ("swell"), typically +20–30% over in-place volume, so a positive compaction factor accounts for haul tonnage.
Some authorities require a soil-management plan above a certain cubic-yard threshold; check before mobilizing.
Most soils swell 20–30% when excavated; clay is on the higher end, sand on the lower. Use a positive compaction factor (e.g., +25%) so your haul tonnage matches the loose volume coming out of the hole.
It depends on volume, location, and what you're digging near. Most municipalities have soil-management or fill-control bylaws above a certain cubic-yard threshold. Always call locates before any dig.
Yes. Set the wastage allowance (typically 5–10%) to cover the over-dig that always happens at the perimeter when an excavator scoops outside the design line.